Renewal- Amendment Environmental Impact Assessment Studies

Study for the amendment of 100838/16.10.06 JMD for the approval of environmental terms of the road section Nea Moudania Interchange - Poteidea bridge in Chalkidiki (EIA 332)

Study for the amendment of 100838/16.10.06 JMD for the approval of environmental terms of the road section Nea Moudania Interchange - Poteidea bridge in Chalkidiki (EIA 332):

The proposed amendment relates solely to the side network of the artery between the settlements of Nea Moudania and Potidaia. The left side road will be moved closer to the main artery.

 

Assignment Authority: Egnatia Odos SA

 

 

Renewal of Common Ministerial Decision/ Approval of Environmental Terms 130437/30-06-2003 of Ilarion Hydroelectric Project (EIA 329)

Renewal of Common Ministerial Decision/ Approval of Environmental Terms 130437/30-06-2003 of Ilarion Hydroelectric Project (EIA 329):

This is the study for the renewal of the environmental terms of Ilarion Hydroelectric Project. The dam of the project is made from gravel with impervious core, will have a maximum height of 130m from the foundation and a total volume of 8x106m3.

The catchment area of the project is approximately 5005 km2, the total volume of the reservoir is 520x106m3and active storage capacity of 412x106m3. The station is comprised of two units with turbines, has a power 76,5 MW and will produce 415GWh annually.

Assignment Authority: PPC

Renewal of no 84978/24-12-2002 JMD AET for the project "New Pipe for Water Supply of SES Kardia and Agios Dimitrios from Polyphytos Reservoir " (EIA 323)

Renewal of no 84978/24-12-2002 JMD AET for the project "New Pipe for Water Supply of SES Kardia and Agios Dimitrios from Polyphytos Reservoir " (EIA 323):

The project of the new pipeline is located in Kozani Prefecture within 15km from the city of Kozani. Based on the approved EIA, the project briefly included the construction of two new pumping stations, one new 15km pipeline and other related small-scale projects to carry water for the water supply of SES of Kardia and Agios Dimitrios from the Polyphytos reservoir in Kozani Prefecture.

Assignment Authority: PPC S.A.

Amendment of no. 197165/28-3-2012 MD (Approval of Environmental Terms for the Dam Skopou-Papadias) (EIA 322)

Amendment of no. 197165/28-3-2012 MD (Approval of Environmental Terms  for the Dam Skopou-Papadias and relative works in Florina regional unit (EIA 322):

The proposed amendment relates  to the environmental approval of the water supply project of the Aqueduct of Municipal Unit of Meliti  using the reservoir of Papadia.  The project includes the construction of a steel 200mm diameter pipe and 1.530m length, for the water supply of the town of Meliti. The project is carried out in application of No. 197165/28-3-2012 MD AET, whereby there is a requirement  for the provision  of 1,27x106m3 as a permanent ecological flow 1,0x106m3 for domestic water supply and 4,0x106m3 for irrigation within the irrigation period May - September.

Assignment Authority: PPC S.A.

Amendment of no. 5031/09/15-1-2010 Decision of the Secretary General of Peloponese (Approval of Environmental Terms for the Harbor of Githion) (EIA 321)

Amendment of no. 5031/09/15-1-2010 Decision of the Secretary General of Peloponese (Approval of Environmental Terms  for the Harbor of Githion)- Environmental Approval of a Gravel Borrow Pit, within the torrent Ardeli in Selinitsa Gythiou (EIA 321)

The proposed amendment relates  to the environmental approval of a new gravel borrow pit, to obtain a total volume of 40.000m3 of material for the construction of the new Harbor of Githion. The site of the proposed borrow pit is located on the bed of the stream Ardeli, at a distance of about 3,5 km north of the harbor. The area of the borrow pit is 3,5 ha  approximately, while the length of river bed interventions, is approximately 1.188m.

Assignment Authority: Region of Peloponnese  - Directorate of Technical Works

Ammendment - Renewal or the project " WWTP of Panormos Community, Tinos Island " (ER 143)

Ammendment - Renewal of No. 32702/5-1-1995 JMD DET and its subsequent amendments and renewals,  for the project " WWTP of Panormos Community, Tinos Island " (ER 143):

This study is implemented to modify and renew the Decision of Environmental Terms  for the project "Wastewater Treatment Plant of Panormos community, which is situated at Andrew's Well - Athymatistra Isle of Tinos in Cyclades Prefecture". The proposed amendment is to extend the network in order to connect, to the existing WWTP, the nearby settlements (a) Paltia and (b) and Rohari at a second phase and (c) the settlement  of Marla , ie 2400 inhabitants.

Assignment Authority: Region of South Aegean, Panormos Community