STUDY FOR RESTORATION OF THE LIPTOL AREA (NRMS 15)
This involves the development of a Restoration Study of the area occupied by the facilities:
• of the inactive SES of the LIPTOL area
• of the inactive coalbrick factory and Lignite Post-processing plant ,
• of the inactive unit of Carbonization
• and the related transport systems of lignite and by-products
The study includes the following sections:
Existing situation – description of establishments
General description of the equipment – materials –waste
Description of possible deactivation of mechanical/ electrical equipment
Description of possible deactivation of building infrastructure
Description of management of electromechanical equipment – materials -waste – alternative solutions
Description of demolition process of building establishments - alternative solutions
Process of demolition - Management of demolition materials – timetable
Assignment Authority: PPC SA